Macclesfield: Most planning applications taking up to half-a-year to process

By Belinda Ryan - Local Democracy Reporter

27th Jun 2022 | Local News

Macclesfield: Have you become frustrated with a planning application wait? You won't be the only one... (Image - Michal Jarmoluk from Pixabay)
Macclesfield: Have you become frustrated with a planning application wait? You won't be the only one... (Image - Michal Jarmoluk from Pixabay)

If you feel like you have been waiting ages to get planning permission considered in Macclesfield - then don't worry - you're not alone. 

The planning backlog at Cheshire East is double what it usually is and most applications are taking four to six months to determine, according to a council report.

The last two planning meetings – northern planning scheduled for June 8 and strategic planning which should have been held on June 15 – were both cancelled with no official reason being given.

A report on the annual performance, due to be considered by Friday's meeting of the environment and communities committee, says pre-application services have been suspended since the start of 2021 for all but major proposals.

Macclesfield: The overall COVID-induced backlog has reduced from October's high, but still remains huge. (Image - Belinda Ryan)

The report states: "The planning service has been under pressure for several years, with a consistently high level of demand and challenges in retaining and recruiting resources.

Congleton: The COVID-induced backlog has reduced from October's high, but still remains huge.

"During 2020 a significant backlog of planning applications started to build up as productivity and recruitment was further disrupted by the pandemic.

"The backlog peaked at 2,882 in October 2021 but only marginally reduced to 2,654 at the end of March 2022. This is double the normal level of around 1,300 and has had an impact on the capacity of planning officers to engage effectively with customers.

"The calendar year of 2021 saw an 11 per cent increase in all applications compared with the previous year with notable increases in submissions of smaller householder and prior approval applications."

It continues: "The percentage of applications determined within eight weeks for non-major applications has reduced to 81 per cent. However, this includes applicants/agents who agree to one or more extensions to time.

Cheshire East Council claimed to have made significant progress in the Congleton area, but have made no such claims for Macc. (Image - Alexander Greensmith / Macclesfield Nub News)

"Most applications are actually taking four to six months to determine. This has led to a large volume of 'failure demand' chasing progress."

Complaints about delays and lack of communication regarding the planning department have increased.

The council has employed an external company, Capita, to help with the backlog.

"The contract has been in place since September 2021 and ,so far, their officers have determined over 500 applications out of 850 allocated to them, the majority of which are householder applications," states the report, adding the contract covers up to 1,000 applications and has been extended for a further period.

How long have you been waiting for a response? (Image - Alexander Greensmith / Macclesfield Nub News)

The council is still struggling to recruit its own staff and currently has six vacancies in the planning applications team.

The report continues: "Notwithstanding the pressures on the planning service, it continues to approve significant strategic developments in accordance with development plan policies to ensure they are sensitive to their surroundings but also achieving good sustainability.

"Key strategic housing/mixed use developments at Basford, Leighton, and employment sites in Middlewich have been approved.

"Significant progress has been made in bringing forward both residential and employment sites at North Congleton as a new community becomes established.

"Key sites in Crewe town centre as part of wider regeneration work have now also begun with the Royal Arcade site receiving planning approval."

No such progress was revealed for Macclesfield.

A deep dive review of the planning service is currently being undertaken to identify ways to reduce the backlog and a verbal report on that is due to presented at Friday's meeting.

The environment and communities committee meeting takes place on Friday July 1 at 10.30am at the council's HQ at Sandbach, known as Westfields. Located over 15 miles from Macclesfield.

For more information about making a planning application in Macclesfield, please click here.

Got a business or organisation to promote in Macclesfield? Advertise it for FREE on our Local List.

Macclesfield: Have you signed up for our FREE Friday weekly newsletter? It contains each week's top five Macclesfield news stories, and one EXCLUSIVE article?

1400 of you have signed up already. Simply enter your email address on this link.

Free from pop-up ads, or unwanted surveys, Macclesfield Nub News is a quality online newspaper for our town.

You can find us on Facebook and Twitter.

     

New macclesfield Jobs Section Launched!!
Vacancies updated hourly!!
Click here: macclesfield jobs

Share:

Related Articles

Macclesfield Town Hall, Market Place (Macclesfield Nub News).
Local News

What's on in Macclesfield this weekend: Bethlehem Casuals, Christmas cocktail event and more

Residents living in substandard housing are urged to contact their landlord in writing (LDRS).
Local News

Macclesfield residents living in substandard housing urged to contact landlord in writing

Sign-Up for our FREE Newsletter

We want to provide macclesfield with more and more clickbait-free local news.
To do that, we need a loyal newsletter following.
Help us survive and sign up to our FREE weekly newsletter.

Already subscribed? Thank you. Just press X or click here.
We won't pass your details on to anyone else.
By clicking the Subscribe button you agree to our Privacy Policy.